Section A; COST ANALYSIS
SECTION A. 40 points
Question one (20)
Q1] cite and discuss the functions of the different stakeholders in the Bafoussam-Bamenda
road project[10pts]
Q2] failure to plan is planning to fail: how true is this statement in project management? [10
pts]
Question two (20)
From your knowledge in project management:
1). What do you understand by business plan/project proposal? 2 pts
2). Account for the necessity of project plan in project management 8pts
3). Account for the principal components of project proposal 10pts
SECTION B. 30 points
Question three
Describe the tools and techniques for gathering information for risk identification 10 pts
Question four
Describe five dimensions of the environment in project management 5pts
Question five
The information below describes the activities of a project.
s/n activity Preceding activity Duration
1 A / 8
2 B A 5
3 C B 20
4 D A 10
5 E D,B 6
6 F C,E 5
a) Draw the network diagram 5pts
b) With the use of a table, calculate the EST and LST 6pts
c) What is the total duration of the project? 1pts
d) Given that the project was to start on the 1
st
of July, when is it expected to end? 1pts
e) After defining critical path, what is critical path of the project? 2 pts
THE UNIVERSITY OF BAMENDA
FACULTY OF ECONOMICS AND MANAGEMENT SCIENCES
2
nd
Semester Exam Course: Project Management: MGMT306
Credit Value:
Course Lecturers:
Time: Course Status: Date: 2018
Venue: Instruction: